Exhibition

Home > Exhibition > Content
Precautions for the installation and operation of the shot blasting machine
Apr 25, 2018

Matters needing attention in the installation process of shot blasting cleaning machine:

1, host position: when the host is in position, its level and weight must meet the requirements of the drawings.

2. The installation of parts should be carried out from the bottom to the highest.

3, track type or catenary type, roller type should be caused by peripherals.

4. Part of the preliminary test should be done first, and then run normally after normal commissioning.

Attentions of operators in the operation of equipment:

1, we must pay attention to whether the display of its cabinet is normal.

2, all personnel entering the shot blasting room must wear eye glasses and helmets.

3, the operator must check the equipment every day.

These include lubrication and mechanical parts. Lubrication parts such as reducer, hydraulic pressure, mist sprayer and bearing chain. Mechanical parts such as wear of rotating parts and wear of worn parts.

Example: if the shot blasting machine has vibration, it must stop the machine immediately to replace the blade; register the wear condition every day, and change the wearing parts in time.

4, the lubrication part should ensure timely refueling.

5, the directional sleeve must be adjusted and replaced in time.

6. Check the quantity of steel balls every day

 